Panache Lake Road, Whitefish

Project Update

Season Wrap-up Notice- December 12, 2023

Pavement Rehabilitation 
Panache Lake Road, Whitefish

The City of Greater Sudbury has completed the road improvements on Panache Lake Road, from St. Pothier Road to Old Highway 17 (MR55) in Whitefish, for the 2023 construction season.

Work will resume in the spring and is expected to be completed by summer 2024.

A Construction Notice will be issued prior beginning.

Remaining construction work includes: 

  • Surface asphalt placement
  • Permanent line painting 
  • Granular shouldering
  • Miscellaneous repairs if required

Thank you for your patience as we work to improve the roads and infrastructure in your neighbourhood. The City of Greater Sudbury and its contractors are committed to public safety and will monitor the ongoing progress of construction.

Project Timeline:

  • Season Wrap-up Notice- December 12, 2023
  • Construction Notice- July 17, 2023
  • Pre-Construction Notice- April 27, 2023

Please see our Construction FAQs webpage for more information.

Project Manager:
Miranda Edwards
705-923-1350
Miranda.Edwards@greatersudbury.ca