Arena/Event Centre

Sudbury Community Arena Analysis

On September 13, 2022, Council directed staff to produce a background report to update the building condition assessment and operational effectiveness analysis of the Sudbury Community Arena and provide a high-level summary of options for its replacement or renovation. This was shared with Council in July 2023.

Read the report:

On September 26, 2023, staff presented a report that provided information requested by Council at its July meeting regarding a facility renewal option and a broader district development with private sector participation.

Read the report:

On October 24, 2023, Council approved the acquisition of properties on Brady, Shaughnessy and Minto streets and on Romanet Lane. In addition to properties previously acquired on Elgin and Shaughnessy streets the land will be available for redevelopment, an important step as Council considers a new or refurbished arena.

Further Exploration - A New or Refurbished Arena

Council directed staff to further explore options for a new or refurbished arena. This additional analysis will have an estimated combined cost of up to $200,000, funded through the Event Centre Project budget. 

A report will be brought back to Council on April 16, 2024.

Read the reports below:

Arena Report Frequently Asked Questions

Leading up to the April 16 City Council meeting, Councillors submitted questions in writing about these reports and staff provided responses, which you can read below: